Going nuclear: The role of fission in net zero
Despite cost overruns and delays, as designs become increasingly standardised, experts believe nuclear power could play a bigger role in Britain’s energy mix.
By Ben Hargreaves, head of content
Going nuclear: The role of fission in net zero
Despite cost overruns and delays, as designs become increasingly standardised, experts believe nuclear power could play a bigger role in Britain’s energy mix.
By Ben Hargreaves, head of content

One notable generation project that won’t struggle to get a connection to the grid this year is the 3.2GW Hinkley Point C nuclear reactor.
It helps that the infrastructure to connect it is already there, and that there is a long lead time for new nuclear reactors, explains Josh Buckland, director of strategy, commercial and policy at EDF. Getting the connection is an important milestone in the project, he tells Utility Week. “We're going to connect Hinkley Point C to National Grid for the first time, which is exciting,” he says. “That effectively gives us power onsite as we start planning for commissioning, where integration with the grid is key.”
Ninety-five per cent of the civil engineering works at Hinkley Point C, which features two EPR reactors (Units 1 and 2), are now complete and the reactor pressure vessels are in place. The next phase is the fitting out of all mechanical, electrical and heating, ventilation and air conditioning systems. The two units require a combined 10,000km of cable and 370km of pipework. Other key milestones include adding two giant Arabelle steam turbines, one for each unit, with installation of the turbine for Unit 1 already underway. Engineers are also planning how to bring water in from the Bristol Channel to cool the reactor systems.
EDF’s current target is for Unit 1 to start producing electricity in 2030. Unit 2 is expected to follow a year or so later. Hinkley Point C was initially slated to start generating in 2025 and to cost £18 billion, but EDF is now estimating a final bill of £35 billion (in 2015 prices).
The near doubling in cost means that productivity improvements are vital. The hope is that lessons learnt at Hinkley Point will inform the development of the new nuclear power station at Sizewell C, which also features two EPRs with a total of 3.2GW capacity, and in which EDF holds a minority stake (the government is the single largest shareholder of Sizewell C with almost 45%).
With efficiency in mind, Buckland notes that at Hinkley Point, the “core civil activities” have been delivered 20% to 30% faster on Unit 2 than Unit 1. There has also been an increased level of modularisation (not to be confused with small modular reactors, more of which later). “We recently lifted a 740t, two-storey building of 12 rooms as a single modular unit into place with the heavy-lift crane,” Buckland says. “That gives you a sense of scale: it's no longer just work on site – a lot of work is happening offsite or near the site and then being lifted in situ, and that is really driving performance.”

Partner commentary:
The reactor is only half the build
Nuclear's cost debate tends to focus on the reactor. But a reactor can only be delivered as fast as the site around it. Power distribution, water, roads, rail, foundations and security all have to be designed, upgraded and maintained, often while the site stays live. This work is easily overlooked when attention is on the reactor.
Another example of a productivity boost is improvements in welding times, which have decreased by about 20%.
For Unit 2, about 60% of the civil construction is modular, which is a “real progression from Unit 1”, says Buckland. “It means more activity can happen offsite in controlled factory environments where work takes place 24/7. The hope is that you can use that learning to go even quicker and potentially increase the level of modularisation at Sizewell C.”
Sizewell C is essentially intended to be a copy of Hinkley Point C. “We think of Sizewell C as UK EPR Units 3 and 4, and Hinkley as Units 1 and 2,” Buckland says. “They're on a trajectory where you take learnings and know-how and apply them unit by unit in a coherent way. That benefits the supply chain, because they're essentially repeating a process. It also means you can speed up construction.”
But these benefits are much more likely to be realised if projects aren’t delayed. It is therefore vital that there isn’t a “significant gap” between Hinkley Point C and Sizewell C, says Buckland. “It’s one of the reasons it was important to get Sizewell C underway, because [supply chain] know-how can fall away quite quickly. We could lose skilled workforce, as could our contractors.
“There are competing demands from other sectors and – in the case of the EPR in particular – developments in France which will create extra competition for capability and workforce. So what's important is seeing projects come through sequentially.”
Contractor Jacobs is part of the team at Sizewell C, doing initial planning in ground engineering, tunnelling, and the development of seawater intakes and outfalls. “Depending on where the plant is physically located, there'll be some bespoke designs,” explains Alan Fotheringham, global market solutions director, low carbon, at Jacobs. “But in effect, what we're trying to achieve is a repeatable design that becomes standardised – lower cost, fewer mistakes, higher quality. You almost take a manufacturing approach.
“Sizewell C and Hinkley Point C are exactly the same nuclear reactor – it's virtually a lift-and-shift of the design from one location to another.”
Could nuclear do more?
Assuming (and it is a big assumption) that Sizewell C goes according to plan, is there potential for nuclear to create a larger part of the energy mix as we approach net zero?
Ed Hezlet, head of energy at thinktank Onward, says current plans at Hinkley Point C and Sizewell C plus three potential Rolls-Royce small modular reactors (SMRs) provide a pathway to 9GW of generation capacity. “I'm firmly of the view that if we can get the cost structure in the right place, there's potential to push much, much more aggressively on that,” he says. “Hinkley is scheduled to cost £15,000 a kilowatt. If we can get the cost down to the original estimates for Hinkley Point C – around £7,500 a kilowatt – then I think there's a very strong argument for doing [more nuclear].”
New nuclear would cut the amount of transmission infrastructure that needs to be built and provide the UK with a baseload of clean power, he adds. “So I think the UK should be more ambitious – but it has to get the cost right if that's going to work.”
Buckland can also envisage more large-scale reactors being built. “Ultimately, government and the system operator have to look at the needs case and think about what's right given other investments across the system, and what's happening in terms of electricity demand,” he says. “If they take the view there's a case for additional nuclear capacity, given we're building two EPR projects – four units – it would make sense to drive that replication into a third project.”
Original estimated cost of output per kilowatt-hour of Hinkley Point
Current estimated cost of output per kilowatt-hour of Hinkley Point, according to Onward
Nuclear has historically represented about 20% of the energy mix but currently provides just 12% of our electricity. Sizewell C and Hinkley Point C could boost that to about 15%. But a future energy system has the potential to create 550TWh hours of demand for electricity versus around 290TWh hours today, Buckland believes. “We're more interested in the proportion of power that comes from nuclear than in gigawatt targets because what really matters is how far we electrify the economy. Given the backbone of the system will be renewables, a slug of firm, always-on, clean nuclear baseload feels to us like a very sensible thing to target.”
SMRs are expected to play a part. These projects are at a very early stage, not just in the UK, but globally. From more than 130 designs, only two SMRs are operating (in Russia and China), but several Western projects are in the process of being built. The Rolls-Royce 470MW SMR is the UK’s chosen design and is earmarked for the Wylfa nuclear site in Wales. French supplier Assystem, which is also involved in Hinkley Point C, is providing design support to the Rolls-Royce programme.
Jay Bhart, Assystem key account director, says the advantage of SMR technology is the ability to manufacture it offsite. “As with automotive or any other type of production facility, as soon as your volume goes up, your costs effectively come down, your supply chain becomes more robust, and your quality improves,” he says. “None of those elements come into play if you're just making ones or twos. If you're making a bespoke piece of plant, it's always going to be bespoke. If you need to modify, change or service it in future, there's always going to be a bespoke element to that.”
Fotheringham of Jacobs believes SMRs could play a much bigger role than currently envisaged. “I think SMRs – either with a regulated utility or a private investor, behind the meter, for example – will feature more prominently in future.” For example, Jacobs has already created an SMR design for Nvidia, designed to power a 1GW data centre and featuring two 500MW SMRs.
EDF is also in on the act and is in the early stages of developing an SMR with US nuclear company Holtec in the Megawatt Valley, the site of old coal-fired power stations on the River Trent. It is thought new data centres could be sited there. The 300MW Holtec design will need to complete the nuclear generic design assessment (GDA) process before it is built in the UK. It has passed the first two steps of the GDA, but the final step, the detailed design assessment, will take place later during site-specific nuclear licensing and environmental permitting.
“One of the key priorities is ensuring that as Holtec pursues regulatory approval in the US, we replicate as much as possible of the design here,” says Buckland. “We want to avoid a redesign process for technology developed in another country that we also want to deploy in the UK.”
Hezlet agrees that SMRs could help boost nuclear’s role in the energy system. He argues that a more “nuclear-centric future” could target over 20GW of power by 2050 by developing a much bigger fleet of SMRs – 15 Rolls-Royce units, for example – and another two large scale projects.
Encouragingly for those who believe we should make more of nuclear, there is agreement on its role, says Buckland. “We've got political consensus on the role of nuclear. It's very much seen as a complement to the renewable backbone of the system.
There is political consistency.” The UK would benefit from taking a similar approach to France when it comes to the technology, adds Bhart. “When France started its nuclear journey, it took a strategic direction. It had a robust, committed vision of where it wanted to get to, regardless of which government came in.
“That replication created a fantastic industry in France in terms of the workforce, skills, supply chain and enduring capability, regardless of what's happening economically. It's there, it's stable, it's sustainable – you're not getting the price hikes you've seen in the UK. They've secured their energy infrastructure. Policy-wise, there's a massive lesson.”
Experts agree that the government should move to implement the recommendations of 2025’s Fingleton Review, which argued the UK had become the most expensive place in the world to build nuclear projects and blamed a fragmented, overly cautious regulatory system that produced costly decisions out of proportion to actual risks. The review (echoing the current enthusiasm for modularisation) also criticised recent projects for over-engineering parts where off-the-shelf items could have been used.
Buckland notes: “One of the experiences we've had in nuclear is that regulation has sometimes caused problems, delays and complexity. The review, and the support it's had from all the individual regulators and licensees, has created a real groundswell of momentum for doing things better and driving better outcomes.”
Hezlet says that the Fingleton Review has important things to say about the tolerability of risk in the sector. “Clearly, we’ve managed nuclear safety very well in this country and we absolutely need to keep to that. But if you have a regulator whose legal job is to push for more safety upgrades, and an industry that struggles to challenge disproportionate cost additions, you get a ratcheting effect. The people building the reactors don’t want to upset the regulator, and the regulator is incentivised to push for more and more safety.”
There is a need to firmly establish what the “true tolerability” of risk is. “We need to understand the correct trade-off, and government defining that level of tolerability would be very helpful indeed.”
“One of the experiences we've had in nuclear is that regulation has sometimes caused problems, delays and complexity.”
Josh Buckland, director of strategy, commercial and policy, EDF